Moto-Lita

Nov 2019 - July 2020 | Steel Portal Frame

Client

Moto-Lita

Location

Weyhill, Andover, Hampshire

Duration

8 Months

The Project

The new facility is a steel portal frame measuring 45m x 17m comprising two floors. The ground floor houses the factory, workshops, and showroom while the first floor contains the offices and stores. Externally there is a tarmac parking and delivery area.

The building is founded on mass concrete pad foundations and the ground floor is a ground bearing concrete slab. The surface water drainage soaks away in five soakaways under the tarmac area, while the foul drainage enters the existing foul drainage run at a manhole in the south east corner of site.

The building is fed with three high voltage cables and a 25mm water pipe into the plant room as well as BT fibre and copper cables.  Solar panels are fitted to the roof generating 39,300kWh per annum.

The building is heated with underfloor heating in the office and showroom areas, the underfloor heating and hot water for the building is heated through an air source heat pump situated outside the plant room. The factory area of the building is heated by electrical panel heaters and ceiling mounter IR heaters.

A bespoke dust extraction duct system has been installed to the factory to ensure the factory complies with DSEAR regulations. All dust is gathered in a dust collector outside the building in the north east corner.

 

 

 

 

Browse our other Construction Projects

Delivering a new steel-framed storage facility in Cornwall

Nationwide Engineering has returned to Cornwall to commence a new construction project for Britannia Lanes at Holmbush Road, St ... Explore More

BARC: Accelerating Development at Thruxton Circuit

Nationwide Engineering successfully delivered the first phase of works at Thruxton Circuit, completing the extension of the Thruxton Centre ... Explore More

Netherhampton Farm

The homes have been carefully constructed using hand-cut Lincolnshire stone to mirror the original farm buildings and blend in ... Explore More

Warminster Starter Units

The site is located at Furnax Lane, Warminster. The three structures are steel frame with mezzanine levels over a ... Explore More

Storagebase

The site is located on Solstice Park, Amesbury which is a large business park just off the A303. Hibberd ... Explore More

Southern Quarter Gym

The company started promoting itself by opening a small coffee shop which developed into a successful business in itself ... Explore More

Redruth Starter Units

The site also incorporates customer EV parking, HGV access, cycle bays, bin store and landscaping complimented with a traditional ... Explore More

Elliott’s Builders Merchants

This new depot provide 5,500m2 of external concrete pavement storage and 1800m2 of show room & sales floor area.Explore More

Steel Frame at The Bluestone Centre, Amesbury

The Bluestone Centre

The Bluestone Centre is an exciting multi-million-pound development of steel framed Business Units situated on Solstice Park, Amesbury in ... Explore More

Discover Adventure Steel Frame, Coombe Bissett

Discover Adventure

Discover Adventure approached Nationwide Engineering to provide a Value Engineering solution to their new Head Office building based in ... Explore More

Birchall Tea Factory in Amesbury

Birchall Tea Factory

This bespoke 29,000ft2 fully solar powered production facility houses state of the art tea processing machines from Italy. The ... Explore More

Nationwide Engineering Group




Call us on: 01722 421 625 enquiries@nationwideengineering.co.uk
  • About
  • Sustainability
  • Armed forces

© 2026 Nationwide Engineering Group|WEBSITE DESIGNED BY BLUE BEE

  • Privacy Policy
  • Cookie Policy
  • Modern Slavery Act Statement