Wessex Culverts Year 2
Aug 2020 - March 2021 | UV-Lining and Remedial works
Client
Network Rail
Location
Wessex
Duration
7 Months
The Project
UV-Lining and Remedial works to 14 culverts throughout the Wessex region, including extensive vegetation clearance, Ecological Assessments, Natural England and Public interface and licences.
The project involved the remedial works to 15 culverts throughout the Wessex region. Given the nature of the works we identified and engaged all key Stakeholders and those that would be effected with or have an interface on the works. prior to detailed delivery plans and programmes being set.
Access to undertake the works was via a local landowner agreements made in partnership with Network Rail properties.
Where over-pumping across the track was required, possessions were agreed in advance that facilitated temporary UTX pipes being placed between the sleepers and under the rails to allow the pumping of water from outfall to inlet while repairs to the culvert were undertaken.