Emergency rail infrastructure stabilisation works
Emergency parapet wall replacement during critical possession
Client
Network Rail
Location
Nightingale Road Viaduct, Guildford
Duration
52-hour possession
The Project
Emergency rail infrastructure stabilisation worksv
Nationwide Engineering delivered critical emergency works at Nightingale Road Viaduct in Guildford on behalf of Network Rail, successfully completing the removal and replacement of a failing parapet wall during a 52 hour possession.
The scope of works included the removal of a 40 metre section of deteriorating parapet wall and the installation of a BaFix ballast retention system in its place. The intervention was required to mitigate the risk of uncontrolled collapse and to ensure the continued safety and integrity of the rail corridor.
A vacuum excavator was utilised to safely and efficiently remove spent rail ballast and fill material, allowing the works to be carried out in a highly controlled manner. Ancillary activities included the movement and protection of trackside cables, along with the installation of a new trough route.
The works were delivered collaboratively with Nationwide Engineering’s specialist supply chain, ensuring the programme was completed safely, efficiently, and within the constraints of a tightly managed possession.